Old Church Road Reconstruction

Posted on Thursday April 26, 2018

Update (July 10, 2018)

Please note that the anticipated completion date has been revised. The change in date is because of challenges with the excavation and materials.  The contractor is required to, and has been working 5 days per week weather permitting, and is committed to completing the reconstruction project as soon as possible.

ANTICIPATED COMMENCEMENT DATE: April 30, 2018
ANTICIPATED COMPLETION DATE: September 12, 2018 (Revised) 

Update (April 26, 2018)

Crews will be working Old Church Road from Regional Road 50 to Mount Pleasant Road.

Old Church Road will be closed to through traffic for the duration of the project. Local access will be maintained for residents, emergency services, busing, waste collection, etc.

ANTICIPATED COMMENCEMENT DATE: April 30, 2018
ANTICIPATED COMPLETION DATE: July 17, 2018