George Bolton Parkway

Posted on Monday April 17, 2017

map

George Bolton Parkway will be reconstructed from Hwy 50 to Nixon Road. This work will include minor repairs to the storm sewer, replacement of curbs and road reconstruction with 140 mm of asphalt. The driving surface will be reconfigured to include bicycle lanes and a left turning lane. This road is a fully urbanized industrial road and acts as a collector road between Coleraine Drive and Hwy 50. Temporary lane closures are expected on George Bolton Parkway from Hwy 50 to Nixon Road, however, two way traffic will be maintained.

 

 

PROJECT NAME:             George Bolton Parkway Reconstruction Phase 1

 

CONTRACT NO.:              Contract No.  2016-76

 

PROJECT LOCATION:      Town of Caledon (refer to the attached location plans)

 

CONTRACTOR:                C. Valley Paving Ltd.

 

CONTACTS

 

C. Valley Paving Ltd.  (Emergency Contacts):

 

Phillip Del Casale - Cell: 647-505-3950, phillip@cvalley.ca

John Montana – Cell: 416-669-1625

Office Telephone: 416-736-4220

 

Greer Galloway Group Inc.:

 

Bob Fudge, Contract Administrator – Cell: 705-957-4842

Mohammad Shawesh, Inspector – Cell: 514-885-0785

Steve Blakey, Project Engineer – Cell: 613-969-5675

Office Telephone: 613-966-3068

 

Town of Caledon

 

Tim Danyliw, Project Manager – Office: 905-584-2272 x 4171, tim.danyliw@caledon.ca

 

SCHEDULED COMMENCEMENT DATE:         May 1, 2017 

 